In general, it takes 6 to 12 weeks, depending on the complexity of the project and weather conditions.
- Study and administrative procedures: 2 to 4 weeks
- Earthworks and construction: 3 to 8 weeks
- Finishing and commissioning: 1 to 2 weeks